The following provides an overview of construction activities. The timeline is tentative and subject to change due to weather, contractor availability or other unforeseen circumstances.

 
  • Start of construction

    June 22, 2020
  • Utility relocation*

    June 22, 2020-August 15, 2020

    *Work to be performed by utility providers or their contractor

  • Erosion control and vegetation clearing

    June 23, 2020-July 15, 2020
  • Installation of stormwater structures and pipe

    July 15, 2020 -August 29, 2020
  • Construct concrete curbs

    August 3-21, 2020
  • Sidewalk installation

    August 15, 2020-Sept. 25, 2020
  • Install signal modifications at 185th Avenue

    Sept. 15, 2020-Oct. 15, 2020
  • Driveways (concrete)

    Sept. 15-25, 2020
  • Driveways (asphalt)

    Oct. 5-16, 2020
  • Project cleanup

    Oct. 15-30, 2020
  • Project completion

    Oct. 30, 2020