This construction kickoff was active from June 11-28, 2020. Information on this website may no longer be current. Email us for more information.
The following provides an overview of construction activities. The timeline is tentative and subject to change due to weather, contractor availability or other unforeseen circumstances.
-
Start of construction
June 22, 2020 -
Utility relocation*
June 22, 2020-August 15, 2020*Work to be performed by utility providers or their contractor
-
Erosion control and vegetation clearing
June 23, 2020-July 15, 2020 -
Installation of stormwater structures and pipe
July 15, 2020 -August 29, 2020 -
Construct concrete curbs
August 3-21, 2020 -
Sidewalk installation
August 15, 2020-Sept. 25, 2020 -
Install signal modifications at 185th Avenue
Sept. 15, 2020-Oct. 15, 2020 -
Driveways (concrete)
Sept. 15-25, 2020 -
Driveways (asphalt)
Oct. 5-16, 2020 -
Project cleanup
Oct. 15-30, 2020 -
Project completion
Oct. 30, 2020